Major construction Stage 1 commenced late 2011

Stage 1

  • Building handover from December 2014
  • External works completed by late April 2015

Stage 2

  • Complete by mid 2017


Stage 1 milestones
Timing
Key Activity
June 2011
Development approval Stage 1 and draft stage 2
Late 2011
Construction commenced
February 2012 to August 2013 Complete works in rail corridor and over railway lines
August 2013 to late 2014 Continue Stage 1 extension
Late 2014
Progressive handover of Stage 1
April 2015
Complete external works and Stage 1

Stage 2 milestones
Timing
Key Activity
July 2013
Development approval received for final Stage 2 concept
Late 2013
Enabling works (Adelaide Convention Centre car park)
Early 2014 Preliminary works - removal of fixtures and rose garden plus construction of new plaza deck
Late 2014
De-construct existing Plenary building
Mid 2015
Major works to construct new Plenary building
Mid 2017
Project complete