Schedule

Below is a table of the estimated timing of major milestones for the Noarlunga Rail Revitalisation.  

Key milestone Estimated timing

STAGE 1 - Start major construction works
Noarlunga line closed over three weekends

Late 2009 - complete
Complete first stage of track upgrade 12 December 2009 - complete (ahead of schedule)

STAGE 2 - Construction between Noarlunga Centre Interchange and Warradale station commences.
Noarlunga line closed between Noarlunga Centre Interchange and Oaklands Interchange for approximately six months   

Sunday 6 February 2011 

Stage 2 upgrade works complete
Train services resume between Noarlunga Centre and Oaklands Interchange

Sunday 24 July 2011 
STAGE 3 - Remainder of the line 2013
Complete electrification and upgrade of Noarlunga Line 2013

Planning work is ongoing to determine the staging of construction works to upgrade and electrify the entire metropolitan rail network. 

This program of works will consider a range of factors including:

  • minimising the impact on commuters and surrounding residents and businesses
  • options for alternative public transport during construction
  • construction efficiency
  • maintaining access to maintenance facilities for railcars
  • complex  technical and engineering aspects.

Further information about the timing of all rail revitalisation upgrade works will be provided to the community and train customers as it becomes available.

Future works - Stage 3

The track upgrade program is moving back to the Gawler line later this year.

Stage three of the Noarlunga line upgrade (remainder of the line) will be undertaken in 2013, following the completion of the works on the Gawler line.

The next stage of works on the Noarlunga line is currently in the planning phase with exact staging and timing yet to be determined. Current planning suggests that works will commence in mid-2012.

To receive further information as it becomes available please join the project mailing list.